As part of the City's Capital Improvement Project for 2014, an estimated 52,000 ft of roads around the City of Hartford will be milled and paved during the Spring of 2014.

2014 Spring and Summer Paving Map (PDF)

 

Street Limits Milling Dates Paving Dates
Barbour Tower to Westland Completed  Completed
Elizabeth Park Prospect to Asylum Completed Completed
Prospect Ave Park to Warrenton Completed Completed
Hamilton Brookfield to Pope Park Hwy Completed Completed
Wethersfield* Eaton to Airport Completed  Completed
Wethersfield* Airport to E. Elliot Completed  Completed
Flatbush* Brookfield to Chandler Completed  Completed
Market* Morgan St N to Pequot Completed  6/9
Capitol* Hungerford to Broad Completed  Completed
Pleasant St* Market to N Chapel Completed  Completed
 Sigourney* Farmington to Collins  Completed  Completed
 Sisson Ave* Park to Capitol   Completed  Completed
 Sisson Ave* Capitol to Gray  Completed Completed
 Weston St*  Savitt to Jennings Completed Completed
 Windsor St* Trumbull to R.R. Bridge  Completed Completed
 Homestead St* Albany to Garden  Completed 6/19, 6/20
 Baltimore St*  Homestead to Albany Completed  6/19
 Pequot*  Market to End Completed Completed
Farmington Ave * Broad to Sigourney  Completed Completed
Henry St   New Britian to Grandview Completed Completed
 Grandview Terr Henry to White  Completed Completed
Goodwin Park  Hubbard to Maple Ave   Completed  Completed

 Note: Dates are subject to change due to inclement weather

*Means Night Paving

 

Click to Expand Menu [ + ]

Department of Public Works Contact

Department of Public Works
50 Jennings Rd
Hartford, CT 06120
Office: (860) 757-9900
Fax: (860) 722-6215

Office Hours:
8:00am - 5:00pm

HARTFORD CITY HALL ADDRESS: 550 Main Street, Hartford, CT 06103 PHONE: (860)757-9311 HOURS: 8AM - 5PM