2014 Spring CIP Road Construction

Expand DPW Updates Menu [ + ]

Select a Department

2014 Spring CIP Road Construction

As part of the City's Capital Improvement Project for 2014, an estimated 52,000 ft of roads around the City of Hartford will be milled and paved during the Spring of 2014.

2014 Spring and Summer Paving Map (PDF)

 

Street Limits Milling Dates Paving Dates
Barbour Tower to Westland Completed  4/24
Elizabeth Park Prospect to Asylum Completed  
Prospect Ave Park to Warrenton 4/24 - 4/25  
Hamilton Brookfield to Pope Park Hwy 4/25  
Wethersfield Eaton to Airport TBD   
Wethersfield Airport to E. Elliot TBD   
Flatbush Brookfield to Chandler TBD   
Market Morgan St N to Pequot TBD   
Pleasant St Market to N Chapel TBD    
 Sigourney Farmington to Collins  TBD    
 Sisson Ave Park to Capitol   TBD   
 Sisson Ave Capitol to Gray  TBD    
 Weston St  Savitt to Jennings TBD   
 Windsor St Trumbull to R.R. Bridge  TBD   
 Homestead St Albany to Garden  TBD  
 Baltimore St  Homestead to Albany TBD  
 Pequot  Market to End TBD  
Farmington Ave  Broad to Sigourney  TBD  
Henry St   New Britian to Grandview TBD  
 Grandview Terr Henry to White  TBD  
Goodwin Park  Hubbard to Maple Ave  TBD   

 Note: Dates are subject to change due to inclement weather

 

Click to Expand Menu [ + ]

Department of Public Works Contact

Department of Public Works
50 Jennings Rd
Hartford, CT 06120
Office: (860) 757-9900
Fax: (860) 722-6215

Office Hours:
8:00am - 5:00pm

HARTFORD CITY HALL ADDRESS: 550 Main Street, Hartford, CT 06103 PHONE: (860)757-9311 HOURS: 8AM - 5PM