As part of the City's Capital Improvement Project for 2014, an estimated 38,000 ft of roads around the City of Hartford will be milled and paved during the Summer of 2014.

2014 Spring and Summer Paving Map (PDF)

 

Street Limits Milling Dates Paving Dates
Palm St Burnham to Lyme 8/11 8/14 
Chatham Cornwall to Blue Hills    
Sharon St Cornwall to Blue Hills    
Edgewood St Greenfield to Garden    
Magnolia St Greenfield to Albany    
Cabot St Albany to Homestead    
Kent St Homestead to Albany    
Woodland St Farmington to Asylum    
Westerly Terr Albany to Albany    
Terry Rd Westerly to Asylum    
 Prospect Ave Farmington to Asylum    
Henry St  Grandview to Roxbury    
 Mountford St Broad to Maple    
 Victoria Rd Franklin to Campfield    
Hubson St * Capitol thru Pulaski Cir    
 Main St* Cleveland to Capen    
Jennings Rd* 100' W of Leibert to end    
Colt Park   775' Park Rd    
830 Maple Ave Senior Center    
Columbus Blvd* State St Intersection    

 Note: Dates are subject to change due to inclement weather

*Means Night Paving

 

Click to Expand Menu [ + ]

Department of Public Works Contact

Department of Public Works
50 Jennings Rd
Hartford, CT 06120
Office: (860) 757-9900
Fax: (860) 722-6215

Office Hours:
8:00am - 5:00pm

HARTFORD CITY HALL ADDRESS: 550 Main Street, Hartford, CT 06103 PHONE: (860)757-9311 HOURS: 8AM - 5PM